Getting to handover
with the evidence in hand

Buildings are approved with acoustic obligations attached — NCC Part F7 sound insulation for apartments, hotels and residential care, plant noise conditions on the development approval, and interior noise targets for the rooms themselves. We assess plant and building services noise against those conditions, advise on room acoustics and speech privacy, and test separating walls and floors on site so the certifier has measured evidence rather than a product data sheet.

When you need one

+
-

When a development approval carries plant or building services noise conditions that have to be closed out before occupation; when a Class 2, 3 or 9c building needs measured evidence of NCC Part F7 compliance at handover; and when occupants of a completed building complain that rooms are too loud, too reverberant or not private enough.

What the standard requires

+
-

NCC Volume One Part F7 sets the sound insulation required between sole-occupancy units in Class 2, 3 and 9c buildings. Where compliance is shown by testing, the field criteria are set out on the sound insulation testing page.

Plant noise is assessed against the conditions of approval and the Environmental Protection (Noise) Policy 2019. Interior noise and reverberation targets for the rooms themselves come from AS/NZS 2107.

What you receive

+
-

For plant and services: an assessment of the selected equipment against the noise conditions at the nearest receivers, with the location, screening, attenuators or enclosures needed to comply.

For rooms: measurements of noise and reverberation against AS/NZS 2107, with the changes that will bring the space into range.

For sound insulation: field test reports for the certifier.

How long it takes

+
-

A plant noise assessment is a desktop task once the equipment is selected and located — ideally before it is ordered, while a condenser can still be moved on paper rather than on the roof. Room measurements and field testing are site visits once the spaces are complete.

How fees are quoted

+
-

A fixed fee for each stage — plant noise assessment, room acoustics, and field testing — quoted from the plant schedule, the floor plans or the number of tests.

Common questions

If we use deemed-to-satisfy constructions, do we still need testing?

+
-

Deemed-to-satisfy construction complies without testing. But certifiers, developers and owners' corporations increasingly ask for field tests anyway, because workmanship — penetrations, flanking and junctions — decides what the built wall actually achieves.

Why does the code use Rw + Ctr rather than Rw alone?

+
-

Ctr corrects the rating for low-frequency sound such as traffic, bass and footfall. A lightweight wall can score well on Rw and noticeably worse once Ctr is added, which is the figure the NCC uses.

When should plant noise be assessed?

+
-

Once the equipment is selected and its location is known, but before it is ordered. Plant is the most common reason a noise condition is not met, and the cheapest fix is a different location or a quieter unit chosen on paper.

Standards we work to

  • NCC Volume One Part F7 Sound transmission and insulation in Class 2, 3 and 9c buildings
  • ISO 16283-1, -2 Field measurement of airborne and impact sound insulation
  • ISO 10052 Survey method for field sound insulation
  • AS/NZS ISO 717.1, AS ISO 717.2 Rating of airborne and impact sound insulation
  • AS 2021 Aircraft noise intrusion — building siting and construction
  • AS/NZS 2107 Design sound levels and reverberation times for interiors
  • AS 1055 Description and measurement of environmental noise
  • ISO 9613-2 Outdoor sound propagation
  • AS/NZS 1269 Occupational noise management and audiometry
Based in Cairns, working across Far North Queensland.
Send the project details and drawings, and we'll come back with a fixed fee proposal.